Environmental Assessment and Permitting in Canada: The Basics

Before a mine can be built in Canada it usually needs an environmental assessment and then a series of permits, from one or both levels of government. Here is how the federal and provincial processes fit together and how to read permitting news.

An aerial view of autumn wetlands with small ponds and a treeline, under the headline Permitting
Key takeaways
  • An environmental assessment decides whether a project can go ahead and on what conditions. Permits then authorize specific activities, such as building, discharging water or storing tailings.
  • Larger projects can face a federal impact assessment, a provincial or territorial assessment, or both. Governments try to coordinate so that one project gets one review, but the details vary.

Introduction

A mineral discovery is a long way from a mine. In between sit engineering studies, financing and a permitting process that can take years. For many juniors, permitting is the step that sets the timeline more than any other.

Canada's system has two levels. The federal government assesses projects with potential effects in areas of federal jurisdiction. Provinces and territories run their own assessment and permitting systems. This guide explains how the pieces fit, using the federal process and British Columbia's as examples, and how to read a permitting announcement.

An assessment asks whether a project should proceed. Permits say exactly how it may operate.

Part 01

Assessments and Permits Are Different

One decision on the project, many on the details.

An environmental assessment (called an impact assessment at the federal level) studies a whole project: its effects on land, water, wildlife, communities and Indigenous rights, and how those effects could be reduced. It ends in a decision on whether the project can proceed, usually with conditions attached.

Permits come afterward. They authorize specific activities: building and operating the mine, discharging water, building a tailings facility, clearing land. A large mine may need many permits from several agencies.

In BC the sequence is explicit. The Environmental Assessment Office says an environmental assessment certificate is a prerequisite for authorizations or approvals under other provincial or federal statutes.

Part 02

The Federal Impact Assessment

For designated projects with federal effects.

The Impact Assessment Act, administered by the Impact Assessment Agency of Canada, applies to designated projects that are the most likely to have significant adverse effects in areas of federal jurisdiction. The Agency describes five phases:

  1. Planning. The proponent submits an initial project description, the public comments, and the Agency decides whether an assessment is required. If it is, the Agency issues tailored guidelines.
  2. Impact statement. The proponent studies the effects, engages the public and Indigenous peoples, and submits an impact statement.
  3. Impact assessment. The Agency prepares a report and proposed conditions for the Minister of Environment and Climate Change.
  4. Decision. The Minister, or the federal Cabinet if the Minister refers it, decides whether adverse effects are likely to be significant and, if so, whether they are justified in the public interest. The result is a decision statement.
  5. Post-decision. The Agency checks compliance with conditions.

The Act has been amended. In October 2023, the Supreme Court of Canada gave an advisory opinion finding parts of it unconstitutional, and amendments that narrowed the federal role came into force in June 2024. The federal process has continued to change since, so check the Agency's current guidance. The Agency says it aims to complete assessments in about two years, within legislated timelines, and works with provinces, territories and Indigenous governments toward "one project, one review".

Part 03

A Provincial Example: British Columbia

From early engagement to a certificate.

Each province and territory has its own system. In BC, the Environmental Assessment Office runs reviews under the Environmental Assessment Act (2018). Its user guide sets out the phases:

  1. Early engagement. The proponent files an initial project description and engagement plan.
  2. Readiness decision. Whether the project proceeds to an assessment, is exempted or is terminated.
  3. Process planning. The scope and steps of the assessment are set.
  4. Application development and review.
  5. Effects assessment and recommendation.
  6. Decision. Two ministers decide whether to issue or refuse an environmental assessment certificate.

A certificate is legally binding and sets out how the project must be carried out. The certificate sets a deadline, no more than ten years out, to substantially start the project, with a possible one-time extension of up to five years. BC's process also gives participating Indigenous nations a formal role, and ministers are legally required to consider their consent or lack of consent.

Part 04

The Permits That Follow

Where the operating rules are set.

After an assessment, the operating permits set the detailed rules. Two examples show the kind of approvals involved:

  • Provincial mine permits. In BC, mines need a permit under the Mines Act. Reclamation security may be a condition of that permit, held by the province to cover the cost of reclamation if a company defaults.
  • Federal fisheries rules. Environment and Climate Change Canada administers the Metal and Diamond Mining Effluent Regulations under the Fisheries Act. Using water frequented by fish to store mine waste may require a regulatory amendment adding that water body to Schedule 2 of the regulations.

Exploration has its own permits. In BC, for example, most mechanized ground-disturbing exploration, including drilling and trenching, needs a Mines Act permit through a Notice of Work application. That is a much smaller process than an environmental assessment.

Part 05

Reading Permitting News

Which step, which government, what is left.

Junior mining releases use permitting words loosely. A few questions make them clearer:

  • Which step is this? Filing a project description, being told an assessment is required, receiving a certificate and receiving an operating permit are very different milestones.
  • Which government? A provincial certificate does not settle a federal process, or the reverse, unless the release explains how the two were coordinated.
  • Is it an exploration or a mine permit? A drill permit is useful but small compared with mine approvals.
  • What conditions apply? Certificates and permits come with conditions that can affect cost and design.
  • What remains? A good release, or the MD&A, lists the approvals still needed before construction.

The news release reader can help you work through an announcement line by line.

Part 06

What to Check

  • The jurisdiction. Provincial and territorial systems differ in steps and timing.
  • Federal involvement. Whether the project is a designated project under the Impact Assessment Act.
  • Indigenous participation. How consultation and agreements are progressing, which often affects timing.
  • The permit list. The technical report's environmental and permitting section, which Form 43-101F1 requires.
  • Closure obligations. Reclamation security and closure costs, which affect financing.
  • Timelines in the company's own words. Treat any target date as an estimate that depends on decisions outside the company's control.

Read the filings on SEDAR+ and the public registry for the assessment, and speak to your own adviser before making an investment decision.

Frequently asked questions

What is the difference between an environmental assessment and a permit?
An assessment looks at a whole project and decides whether it should proceed and under what conditions. Permits come after and authorize specific activities. In BC, the Environmental Assessment Office says an environmental assessment certificate is a prerequisite for authorizations under other provincial or federal statutes.
Does every mine need a federal impact assessment?
No. The federal process applies to designated projects, which are those most likely to have significant adverse effects in areas of federal jurisdiction. Many projects are assessed only by a province or territory, or not at all if they fall below the thresholds.
How long does an assessment take?
It varies widely. The Impact Assessment Agency of Canada says it aims to complete federal assessments in about two years, but the full path from early planning to final permits can take considerably longer, depending on the project and the jurisdiction.
Does an exploration program need permits?
Usually, but of a different kind. In BC, most mechanized ground-disturbing exploration such as drilling and trenching needs a Mines Act permit through a Notice of Work application, rather than an environmental assessment. Other provinces and territories have their own rules.
Sources
Disclaimer.

This article is published by Bellmare Capital, a brand operated by Apollo Shareholder Relations, for information and education only. It is not investment advice, a recommendation, or an offer or solicitation to buy or sell any security. Bellmare Capital is not a registered investment adviser or dealer, and this is not independent research.

Apollo Shareholder Relations provides paid investor relations, marketing and communications services to public companies, including companies in the sectors Bellmare Capital writes about, and may be compensated in cash or securities. Apollo, its principals, employees and contractors may hold securities of companies discussed and may buy or sell them at any time. Where an article covers a company that pays Apollo, it is labelled Sponsored at the top with the compensation and holdings.

Information comes from public filings and other sources believed to be reliable, but its accuracy and completeness are not guaranteed, and it may be out of date. Small cap and junior resource companies are speculative and volatile, and investors can lose their entire investment. Bellmare Capital and Apollo Shareholder Relations accept no liability for any loss arising from use of this content. Read each company's own filings on SEDAR+ and consult a registered adviser before acting.

Get the next one by email.