Capex, Opex and Sustaining Capital: The Cost Words in a Mining Study

Every mining study carries a table of capital and operating costs. Here is what initial capital, contingency, operating cost per tonne, sustaining capital and closure costs each mean, and why the numbers tend to move between study stages.

Aerial view of an excavator and haul truck on an earthworks site, under the headline Capex and opex
Key takeaways
  • Initial capital is the cost to build the mine. Operating cost is the cost to run it, usually quoted per tonne processed. Sustaining capital keeps it running.
  • Contingency is an allowance for costs the engineers expect but cannot yet itemize. A small contingency on an early study is a reason for caution, not comfort.
  • Cost estimates usually become more detailed, and often higher, as a project moves from a PEA to a feasibility study. Always check the study date and what it includes.

Introduction

When a junior publishes a preliminary economic assessment (PEA), a pre-feasibility study or a feasibility study, the headline is usually the net present value. Behind that number sits a cost table: what the mine would cost to build, what it would cost to run, and what it would cost to keep running and eventually close.

Those cost words have specific meanings, and they move in predictable ways as a project matures. This guide explains each one. We cover the study stages themselves, and metrics such as all-in sustaining cost (AISC), in separate guides, so here the focus is on the cost lines.

The NPV is only as solid as the cost table underneath it.

Part 01

Where the Numbers Come From

The technical report has to show its work.

In Canada, a study disclosed by a reporting issuer is supported by a technical report under National Instrument 43-101, filed on SEDAR+. The form that sets its contents, Form 43-101F1, requires three things relevant here:

  • Capital and operating costs: a summary of the cost estimates, with the major components set out in a table, and an explanation and justification of the basis for the estimates.
  • Economic analysis: the principal assumptions, annual cash flow forecasts, net present value, internal rate of return and payback, and a sensitivity analysis to changes in metal price, grade, and capital and operating costs.
  • Environmental and closure items: a discussion of mine closure, remediation and reclamation requirements and costs, among other permitting and social factors.

The study's news release gives the summary. The technical report gives the detail.

Part 02

Initial Capital

What it costs to get to first production.

Initial capital, also called pre-production or upfront capex, is the spending needed before the mine produces anything saleable. A typical breakdown includes:

  • Direct costs: the processing plant, mine development and pre-stripping, the mining fleet if owner-operated, the tailings facility, power, water, roads and camp.
  • Indirect costs: engineering, procurement and construction management, owner's costs, temporary facilities, first fills and spares.
  • Contingency: an allowance on top of the estimate, discussed below.

Initial capital is the number that decides how much financing a company needs. It is often the hardest hurdle for a junior, because it can be many times the company's market value.

Watch for what is left out. Some studies assume a contractor fleet or leased equipment, which lowers initial capital but raises operating cost. Others place a power line or road outside the project. Neither is wrong, but both change comparisons.

Part 03

Contingency

An allowance for the costs nobody has itemized yet.

Contingency is money added to an estimate for costs that are expected but not yet defined in detail. It is not a reserve for disasters. It reflects how much engineering has been done: the less design work behind a number, the more of it is unknown.

That is why contingency is normally larger, as a percentage, in an early study than in a feasibility study. A PEA that carries a small contingency on a lightly engineered estimate deserves a closer look, not more confidence. The technical report should say what the contingency covers and how it was chosen.

Part 04

Operating Cost

The cost to run the mine, usually per tonne.

Operating cost covers the recurring spending: mining, processing, general and administrative costs, and often site services and transport. Studies commonly express it per tonne of ore processed, sometimes split into mining cost per tonne mined and processing cost per tonne milled.

Per-tonne figures matter because they connect to grade. Suppose a hypothetical open pit has a total operating cost of $40 per tonne processed. If each tonne contains metal worth $60 after recovery, the margin is $20 a tonne before capital and taxes. If the grade falls so that each tonne contains $45 of metal, the margin shrinks to $5. This is the logic behind cut-off grade, which we cover in its own guide.

Studies also convert operating costs into a cost per ounce or per pound of metal. Those figures depend on grade and recovery, and often on by-product credits, so they are not directly comparable across projects without checking the basis. The AISC margin calculator shows how a cost per ounce compares with a metal price.

Part 05

Sustaining Capital and Closure

The spending that continues after the ribbon cutting.

Sustaining capital is spent during production to keep the mine operating at its planned rate: replacing equipment, raising tailings facilities, and ongoing development. The World Gold Council's guidance on AISC treats production-phase open pit stripping and underground development as generally sustaining, and separates out non-sustaining costs, such as spending on new operations or major projects expected to materially increase production.

Expansion capital is the other side of that line. It is money spent to grow output, and it is usually shown separately in a study.

Closure costs cover reclamation and remediation at the end of mine life, and sometimes long-term water treatment. They can be large and they arrive when the mine is no longer earning. Regulators often require financial security in advance. In British Columbia, for example, reclamation security may be a condition of a Mines Act permit, and the province holds it to cover reclamation costs if a company defaults on its obligations.

Part 06

Why the Numbers Move

More engineering usually means more line items.

Cost estimates change between study stages for ordinary reasons:

  • More detail. A feasibility study designs things a PEA only assumed. Detailed design tends to find costs that were not in the earlier estimate.
  • Changed scope. A larger or smaller plant, a different mining method, or new infrastructure.
  • Time. Equipment, labour, energy and reagent costs change. A study from several years ago reflects the prices of its date.
  • Currency. Many inputs are priced in US dollars. A study in Canadian dollars carries an exchange rate assumption.

A higher capital estimate at a later stage is common and is not, by itself, a sign of a bad project. What matters is whether the economics still work at the new figure, and whether the company explains the change.

Part 07

What to Check

  • The study date and currency. Costs date quickly.
  • Initial capital and contingency. How large the contingency is, and what it covers.
  • Owner or contractor mining. It shifts costs between capital and operating lines.
  • Operating cost per tonne. Compared with the value of metal in each tonne.
  • Sustaining and closure capital. Whether both are included over the full mine life.
  • The sensitivity table. How far NPV moves if capital or operating costs rise.
  • Funding. Initial capital set against the company's cash and market value. See reading a junior's capital structure.

Read the full technical report on SEDAR+, and speak to your own adviser before making an investment decision.

Frequently asked questions

What is the difference between capex and opex?
Capital expenditure (capex) buys or builds long-lived assets such as the plant, the mine fleet and infrastructure. Operating expenditure (opex) is the recurring cost of mining and processing ore, usually quoted per tonne.
What is sustaining capital?
Capital spent after the mine is built to keep it producing at its planned rate, such as replacing equipment, raising tailings dams or ongoing underground development. It is separate from expansion capital, which is spent to grow production.
Where do I find a project's cost estimates?
In the technical report filed on SEDAR+. Form 43-101F1 requires a summary of capital and operating cost estimates with the major components set out in a table, and a justification of the basis for them.
Are closure costs included in a study?
They should be discussed. Form 43-101F1 asks for a discussion of mine closure, remediation and reclamation requirements and costs, where the information is reasonably available.
Sources
Disclaimer.

This article is published by Bellmare Capital, a brand operated by Apollo Shareholder Relations, for information and education only. It is not investment advice, a recommendation, or an offer or solicitation to buy or sell any security. Bellmare Capital is not a registered investment adviser or dealer, and this is not independent research.

Apollo Shareholder Relations provides paid investor relations, marketing and communications services to public companies, including companies in the sectors Bellmare Capital writes about, and may be compensated in cash or securities. Apollo, its principals, employees and contractors may hold securities of companies discussed and may buy or sell them at any time. Where an article covers a company that pays Apollo, it is labelled Sponsored at the top with the compensation and holdings.

Information comes from public filings and other sources believed to be reliable, but its accuracy and completeness are not guaranteed, and it may be out of date. Small cap and junior resource companies are speculative and volatile, and investors can lose their entire investment. Bellmare Capital and Apollo Shareholder Relations accept no liability for any loss arising from use of this content. Read each company's own filings on SEDAR+ and consult a registered adviser before acting.

Get the next one by email.