Reclamation and Closure: The Cost at the End of a Mine's Life

Every mine has to be cleaned up, and in Canada the money to do it has to be secured before the damage is done. Here is how closure plans and reclamation security work, and where closure costs show up in studies and financial statements.

Gloved hands pressing soil around a young tree seedling newly planted in grass, under the headline Reclamation
Key takeaways
  • Canadian provinces require a mine to have an approved plan for closure and to post financial security that covers the cost of reclamation if the operator defaults.
  • Progressive reclamation, done during operations, can reduce the security a mine has to hold and the work left at the end.
  • Closure costs appear in NI 43-101 studies and, once a company has an obligation, as a provision in its financial statements.

Introduction

A mine is a temporary use of land. When the ore runs out, someone has to take down the buildings, make the waste rock and tailings safe and stable, deal with water, and return the land to a use the regulator accepts. That work can run for years after the last ounce is sold, sometimes much longer where water needs ongoing treatment.

In Canada the rules aim to make sure the money for that work exists before the mine is built. This guide explains closure plans, reclamation security, progressive reclamation, and where closure costs appear in the documents investors read.

Closure is the one cost every mine is certain to face.

Part 01

What Closure Involves

More than planting trees.

A closure plan sets out how a site will be left. Typical elements include:

  • Removing infrastructure. Buildings, processing plant, power lines and roads that are not needed afterwards.
  • Stabilizing waste. Reshaping and covering waste rock dumps and tailings facilities so they are physically and chemically stable.
  • Managing water. Collecting and treating water that has contact with mine waste, sometimes for a long time.
  • Sealing openings. Closing underground workings and making open pits safe.
  • Revegetation and monitoring. Restoring land cover and checking for years that the work holds.

The cost depends on the size of the disturbance, the chemistry of the waste and, above all, on water. A site whose waste can generate acid drainage can carry a much larger and longer closure obligation than one that cannot.

Part 02

Reclamation Security in British Columbia

The money is posted before it is needed.

British Columbia's government describes reclamation security as financial security that covers the cost of reclaiming a site if a mining company defaults on its obligation. The Province holds it until reclamation is complete. Section 10(4) of the Mines Act allows security to be required as a condition of a permit.

How it works, according to the Province:

  • Site-specific amounts. The chief permitting officer sets the amount and form for each site, reflecting outstanding reclamation liability and environmental and closure obligations.
  • Major mines. Larger mines submit reclamation liability cost estimates under the Major Mines Reclamation Security Policy, interim since April 2022, tied to permit applications, five-year plan updates and annual reclamation reports.
  • Smaller operations. Regional mines are assessed with a reclamation bond calculator.
  • Accepted forms. Cash equivalents, investment certificates (GICs) for small amounts, irrevocable standby letters of credit and reclamation surety bonds.
  • Adjustments. The amount can be lowered for progressive reclamation and raised for new disturbance. Security is released only under the authority of the chief inspector of mines.
Part 03

Closure Plans in Ontario

A plan, a cost estimate and financial assurance.

Ontario takes a similar approach under Part VII of its Mining Act and the regulation made under it. A closure plan is a plan to rehabilitate a site or mine hazard, and it must specify the form and amount of financial assurance to be provided to the Crown. An Ontario ministry policy on publicly posting financial assurance information notes that the ministry holds assurance tied to the estimated closure cost of each site.

Other provinces and territories have their own versions. The common thread is a plan approved before development and money secured against it.

Part 04

Progressive Reclamation

Cleaning up as you go.

Progressive reclamation means reclaiming parts of a site during operations rather than leaving all of it to the end. A mined-out area is reshaped and revegetated while mining continues elsewhere.

It has two practical benefits. It shrinks the work left at closure, and, as British Columbia's framework recognizes, it can reduce the security a company has to hold. For an investor, evidence of progressive reclamation in annual reports is a reasonable sign that closure is being managed rather than deferred.

Part 05

Where Closure Costs Show Up

Studies, then financial statements.

In technical studies. Form 43-101F1, the required format for a technical report under NI 43-101, asks for a discussion of "mine closure (remediation and reclamation) requirements and costs," along with permitting requirements and "any known requirements to post performance or reclamation bonds." In a study's cash flow model, closure costs usually appear near the end of the mine life, which means discounting makes them look small in the net present value. Check the undiscounted figure as well. Our guide to reading a junior mining news release covers how study results are presented.

In financial statements. Once a company has an obligation to restore a site, it records a liability. Under IFRS, a decommissioning, restoration or similar liability is recognized as a provision and included in the cost of the related asset. IFRIC 1 explains that later changes in the estimate, including changes in the discount rate, adjust the cost of the asset, and that the unwinding of the discount each period is recognized in profit or loss as interest expense. Companies often call this an asset retirement obligation, a reclamation provision or a decommissioning provision.

In the cash position. Reclamation security is real money or credit. Cash posted as security is not available for exploration or operations, and a letter of credit typically uses up borrowing capacity. Look for restricted cash or reclamation deposits in the balance sheet notes.

Part 06

For Explorers

Most juniors are years away from a mine. Their closure exposure is usually limited to exploration disturbance: drill pads, trails and camps, often covered by smaller permit-specific security. That changes when a project moves toward development, when the closure plan and cost estimate become part of permitting and of every economic study. An acquisition of an old or past-producing property can also bring legacy obligations with it, so read the terms.

Part 07

What to Check

  • The closure estimate in any study, discounted and undiscounted, and whether it includes long-term water treatment.
  • The bonding requirement described in the technical report.
  • The provision in the financial statements and how it has changed year to year.
  • Restricted cash or reclamation deposits, which reduce the cash actually available.
  • Progressive reclamation reported in annual filings.
  • Legacy obligations on any acquired property.

This is general information, not advice. Read the filings on SEDAR+ and speak to your own adviser before making any decision.

Frequently asked questions

What is reclamation security?
Money or a financial instrument posted with the government to cover the cost of reclaiming a mine site if the company defaults. In British Columbia it can take the form of cash, certain investment certificates, irrevocable standby letters of credit or surety bonds.
Does a junior explorer have to post reclamation security?
Exploration work that disturbs land is generally permitted and can carry its own security requirement, usually far smaller than for a mine. The amount depends on the province, the permit and the disturbance.
Where do I find closure costs for a project?
In an NI 43-101 technical report, Form 43-101F1 asks for a discussion of mine closure requirements and costs. For an operating company, the financial statements show a provision for closure or decommissioning obligations.
Why do closure costs matter if they come at the end?
Security usually has to be posted up front, which ties up cash or credit. And the estimate can rise over time, which adds to the liability.
Sources
Disclaimer.

This article is published by Bellmare Capital, a brand operated by Apollo Shareholder Relations, for information and education only. It is not investment advice, a recommendation, or an offer or solicitation to buy or sell any security. Bellmare Capital is not a registered investment adviser or dealer, and this is not independent research.

Apollo Shareholder Relations provides paid investor relations, marketing and communications services to public companies, including companies in the sectors Bellmare Capital writes about, and may be compensated in cash or securities. Apollo, its principals, employees and contractors may hold securities of companies discussed and may buy or sell them at any time. Where an article covers a company that pays Apollo, it is labelled Sponsored at the top with the compensation and holdings.

Information comes from public filings and other sources believed to be reliable, but its accuracy and completeness are not guaranteed, and it may be out of date. Small cap and junior resource companies are speculative and volatile, and investors can lose their entire investment. Bellmare Capital and Apollo Shareholder Relations accept no liability for any loss arising from use of this content. Read each company's own filings on SEDAR+ and consult a registered adviser before acting.

Get the next one by email.